Loop Line Upgrade Project construction to recommence

Compressed image

Loop Line Upgrade Project construction to recommence

Compressed image

Loop Line Upgrade Project construction to recommence

Compressed image

Following a brief pause to finalise supplier arrangements for remaining work packages, we’re pleased to confirm construction to complete the Loop Line Upgrade Project will recommence within the next two months.

This will kick off the final construction phase of the project and will bring us one step closer to delivering an upgraded heritage rail experience for the region.

What we have undertaken to date

Significant progress was made in 2024, including replacing over 18,000 sleepers across the 18.7km section of track between Buxton and Colo Vale, installation of new infrastructure at Colo Vale to permit locomotives to run-around for the return journey, replacement of the Ligar Street Underbridge, initial hazardous tree removals, and initial upgrades to five level crossings along the line.

Remaining works to be completed

The following works will be undertaken to complete the Loop Line Upgrade Project, between now and early 2026:





Work

Locations

Impact to community

Anticipated Timing

Level crossing road resurfacing, line marking and signage installation

* East Parade, Buxton South * Balmoral Village * Railway Parade, Balmoral * Coates Road, Hill Top * Fitzroy Street, Hill Top

Temporary level crossing closures between and traffic diversions

Mid 2025

Geotechnical rectification works

Various cutting locations between Buxton and Colo Vale

Minimal impact

Mid 2025

Hill Top Platform repair

Hill Top Station

Some vehicle/truck movements adjacent to Hill Top Playground

Mid 2025

Various track repairs

Various locations between Buxton and Colo Vale

Minimal impact

Mid 2025

Targeted fencing

Various locations between Buxton and Colo Vale

Minimal impact

Late 2025

Track ballasting and resurfacing works

Various locations between Buxton and Colo Vale

Some daytime noise with ballast trains travelling through level crossings

Late 2025

Pedestrian level crossings installation

* Wattle Street, Hill Top * Linda Street, Hill Top * Balmoral Township

Existing pedestrian crossings to close while works occur

Late 2025

Final vegetation clean-up

* Buxton – Colo Vale

Minimal impact

Late 2025

Colo Vale Station reactivation

Colo Vale Station

Minimal impact

Late 2025

Signalling installation

Various locations between Buxton and Colo Vale

Minimal impact

Late 2025

While an exact opening date is still to be confirmed, THNSW anticipates the majority of works will be completed by the end of 2025, ready for testing, with the extension expected to open in 2026.

PLATFORM SECURED FOR HILL TOP

Following strong advocacy from residents of Hill Top and continued discussions with the NSW Government, the existing station platform at Hill Top village will be secured and reactivated in time for the line’s reopening.

This reactivated platform will ensure safe access for passengers to alight and board heritage trains, operating between the NSW Rail Museum at Thirlmere and Colo Vale.

The platform reactivation will complement the newly installed play equipment and play area, which were funded through grants secured by the Hill Top Community Association and Wingecarribee Shire Council, with support from Transport Heritage NSW and the NSW Government.

KEEP INFORMED

We’ll continue to keep the community updated as work progresses. For the latest news and project milestones: